A practical course in objective scoring, clear ownership and escalation for IT delivery.
Study time: approx. 16-17 hours | Self-paced | 11 modules
This course teaches a consistent, objective approach to managing risk across IT programmes and projects. It is written for a mixed audience: project and programme managers, delivery leads, architects, service managers, commercial staff and senior leaders. No prior risk management qualification is assumed.
The central idea is simple. Risk management fails most often not because people do not identify risks, but because they score them subjectively, assign them to the wrong people, escalate them inconsistently and let mitigation plans drift. This course fixes that by giving you defined criteria, clear ownership rules and a repeatable governance structure.
Suggested study time: 11 modules of around 90 minutes each (roughly 16 to 17 hours in total, or two days of facilitated delivery).
Each module contains: an overview, learning outcomes, content, a worked example, exercises with suggested answers, and key takeaways.
By the end of the course, you will be able to:
| Stage | Modules | Question answered |
|---|---|---|
| Foundations | 1. Foundations of Risk Management 2. Risk Categories |
What is a risk and how do we classify it? |
| Assessment | 3. Objective Scoring 4. Risk Tolerance and Appetite 5. Cost of the Risk and Cost of Mitigation |
How serious is it, is it tolerable, and what does it cost? |
| Response | 6. Risk Response Strategy 7. Risk Budget and Contingency |
What do we do about it and how do we fund it? |
| Governance | 8. Governance and Ownership 9. Commercial Risk and Working at Risk 10. Communication and Reporting |
Who owns it, who must know, and what commercial exposure can we carry? |
| Integration | 11. Putting It All Together | How does it all work together? |
Several exercises use one shared scenario so that learning builds up across modules.
Project Meridian is a nine-month, fixed-price programme (£4.8m) in which your company migrates a client's on-premises finance and order management systems to a cloud platform. The work includes:
The client has asked you to begin build work next month while contract variations are still being negotiated. You will meet this scenario again in Modules 3, 5, 6, 7, 8, 9 and 11.
The end-of-course assessment is a 25-question multiple-choice quiz covering Modules 1 to 11. You must answer at least 20 questions correctly (80%) to pass and unlock the course badge and certificate. You can retake the quiz as often as you like. Module 11 also includes a practical assessment: a scored risk register, mitigation plan, contingency calculation, escalation decisions, W@R assessment and an executive summary.
| Template | Contents |
|---|---|
| Scoring criteria guide | Probability, impact (schedule, financial, reputational, technical) and proximity bands |
| Risk register | Fields listed in Module 1, plus inherent and residual scores |
| Tolerance table | Thresholds by category and project value |
| Cost and EMV worksheet | Cost of the risk, mitigation cost, EMV before and after |
| Mitigation plan | Objective, actions, owners, dates, cost, expected effect, fallback |
| Path to Green tracker | Milestones, expected scores, triggers |
| DAM and escalation matrix | Owner levels, category adjustments, triggers, timescales |
| W@R policy checklist and register | Limits, cover, approvals, stop-work dates |
| Contingency log | Original, drawn, committed, remaining, release |
| Communication plan | Audience, content, format, frequency, owner |
| Risk report pack | Top risks, heat map, trend, Path to Green status |
The scoring bands, tolerance thresholds, DAM levels, W@R limits and contingency percentages in this course are illustrative. Replace them with your organisation's own values before using them in practice.
Course author: Tim Williams
Last updated: November 2026
This course draws on widely used risk management practice, including cause-event-effect risk statements, probability and impact scoring, expected monetary value, risk tolerance and appetite, and tiered governance and escalation. The figures, thresholds and policies used are illustrative and should be replaced with your organisation's own values.
Copyright (c) 2026 Tim Williams. Made available under a Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International Licence (CC BY-NC-SA 4.0). Full terms: https://creativecommons.org/licenses/by-nc-sa/4.0/
This course was drafted with the assistance of an AI model (Claude, from Anthropic) and was reviewed, edited and approved by the course author.
This module sets the vocabulary and structure for the rest of the course. You will learn what a risk is, how it differs from an issue, why consistent and objective risk management matters in IT delivery, and how the risk lifecycle and risk register work in practice.
Estimated study time: 90 minutes.
By the end of this module you will be able to:
A risk is an uncertain event or condition that, if it occurs, has a positive or negative effect on objectives such as time, cost, quality, security or reputation. Three features matter:
A good risk statement has three parts: cause, event, effect. For example:
Because the third-party payments provider has not yet published its API specification (cause), integration design may start on incorrect assumptions (event), leading to rework and a delay of up to six weeks (effect).
Weak statements such as "integration might be a problem" cannot be scored, owned or mitigated.
| Risk | Issue | |
|---|---|---|
| Status | May happen | Has happened or is certain |
| Managed by | Mitigation, monitoring, contingency | Resolution, action plans |
| Scored using | Probability, impact, proximity | Impact and urgency only |
| Example | Key engineer may resign | Key engineer has resigned |
When a risk materialises it becomes an issue. At that point the risk register entry is closed (or converted) and the issue is managed through issue management, drawing on any contingency set aside.
In IT delivery, poor risk management typically shows up as:
A structured framework addresses each of these: defined scoring criteria, tolerance thresholds, a Designated Authority Matrix (DAM), an escalation plan and a Working at Risk (W@R) policy. These are the building blocks of the following modules.
The lifecycle is continuous. Risks are reviewed on a regular cadence (see Module 10) and new risks are added throughout delivery.
| Role | Typical responsibility |
|---|---|
| Risk owner | Accountable for managing the risk to an acceptable level |
| Action owner | Delivers specific mitigation actions |
| Risk manager or PMO | Maintains the framework, challenges scoring, consolidates reporting |
| Project or programme manager | Ensures risk management is performed and reviewed |
| Senior leadership | Sets tolerance, approves high-level responses, funds contingency |
The risk register is the single source of truth. Minimum fields:
Raw concern: "The data migration worries me."
Improved risk statement: "Because 12 years of legacy data contains inconsistent formats and duplicate records (cause), the migration may fail validation during user acceptance testing (event), resulting in a go-live delay and additional cleansing effort (effect)."
Exercise 1.1: Risk or issue? Classify each as a risk or an issue and justify your answer.
Exercise 1.2: Rewrite the risk. Rewrite each vague statement as a cause, event, effect risk statement.
Exercise 1.3: Spot the gaps. Review the sample register extract below and list every missing or weak element.
| ID | Risk | Owner | Score | Mitigation |
|---|---|---|---|---|
| 14 | Testing may overrun | Team | High | Try to finish on time |
Categorising risks lets you group them for reporting, apply the correct impact criteria and route them to the right owners. This module introduces a core set of categories for IT delivery, explains how to handle risks that span several categories, and shows how category influences ownership and mitigation.
Estimated study time: 90 minutes.
By the end of this module you will be able to:
Categorisation helps you to:
| Category | Definition | IT examples |
|---|---|---|
| Financial | Risks affecting cost, revenue, margin or funding | Cost overruns, currency movement, licence price increases, unrecoverable work |
| Reputational | Risks affecting trust and standing with clients, regulators, staff or the market | Public data breach, repeated missed deadlines, negative client escalation |
| Technical | Risks affecting solution design, performance, security, integration or service | Architecture limitations, integration failure, scalability, cyber vulnerabilities |
| Category | IT examples |
|---|---|
| Schedule | Dependency delays, late client decisions, environment availability |
| Contractual and legal | Liquidated damages, ambiguous scope, data protection obligations |
| Resource and people | Key person dependency, skills gaps, attrition |
| Supplier and third party | Subcontractor failure, vendor end of life, delayed deliverables |
| Security and compliance | Regulatory breach, failed audit, weak access controls |
| Operational | Service disruption, support readiness, knowledge transfer |
Each organisation should agree a fixed list so everyone uses the same labels.
Many IT risks span categories. A delayed integration is technical in cause, schedule in effect and financial in consequence. To avoid confusion:
Example: "Unpatched server vulnerability may be exploited, leading to data loss, fines and loss of client trust."
| Category | Typical owner | Typical mitigation |
|---|---|---|
| Financial | Commercial or finance lead | Change control, hedging, contract terms |
| Reputational | Senior delivery or client lead | Communication plans, early engagement |
| Technical | Architect or technical lead | Design change, prototypes, additional testing |
| Supplier | Supplier or procurement manager | Performance clauses, backup suppliers |
Risk: "The logistics provider's API is still in beta and may change before go-live, forcing rework of the integration layer."
Exercise 2.1: Categorise. For each risk, give a primary and up to two secondary categories.
Exercise 2.2: Build your category list. In groups, agree a category list for your own organisation (no more than eight), with one-line definitions. Test it with five real risks from your current work. Which risks were hard to place, and why?
Subjective scoring is the most common reason risk registers cannot be trusted. This module shows how to replace opinion with defined criteria bands so that any two trained assessors reach the same score. You will score probability, impact and proximity, calculate an overall score and read it from a matrix.
Estimated study time: 90 minutes.
By the end of this module you will be able to:
If two people are asked "how bad would a delay be?", one may say "moderate" for six weeks and another "severe". Neither is wrong, because "moderate" has no definition. The result is:
The solution is defined criteria: numeric or factual bands, agreed in advance, so that the facts decide the score and not the person.
This course uses a 1 to 5 scale for each factor. Organisations should adapt the bands to their own size and contract values.
Overall score = Probability × Impact (range 1 to 25), with Proximity used to set priority and urgency.
| Score | Label | Likelihood of occurring | Guidance |
|---|---|---|---|
| 1 | Very low | Less than 10% | Would take unusual circumstances |
| 2 | Low | 10% to 30% | Has happened rarely on similar projects |
| 3 | Medium | 31% to 50% | Has happened on some similar projects |
| 4 | High | 51% to 75% | Likely, with early signs visible |
| 5 | Very high | More than 75% | Expected unless action is taken, or already starting |
Where possible, ground the percentage in evidence: historical data, lessons learned, supplier track record.
Impact is scored against each relevant dimension, and the highest score applies. This prevents a severe reputational risk from being hidden by a small financial figure.
Schedule impact (time-based criteria):
| Score | Rating | Delay to a milestone or go-live |
|---|---|---|
| 1 | Low | Less than 2 weeks |
| 2 | Low | 2 weeks to less than 1 month |
| 3 | Medium | 1 month to less than 2 months |
| 4 | Medium | 2 months to 3 months |
| 5 | High | More than 3 months |
Financial impact (as a percentage of contract or project value; on Meridian's £4.8m, 1% is £48,000):
| Score | Rating | Cost impact |
|---|---|---|
| 1 | Low | Less than 1% |
| 2 | Low | 1% to less than 2% |
| 3 | Medium | 2% to less than 5% |
| 4 | Medium | 5% to 10% |
| 5 | High | More than 10% |
Reputational impact:
| Score | Rating | Description |
|---|---|---|
| 1 | Low | Noticed within the team only |
| 2 | Low | Informal complaint from the client project team |
| 3 | Medium | Formal complaint, or client management concern raised |
| 4 | Medium | Client executive escalation, or trade press coverage |
| 5 | High | Loss of a key client, regulator involvement or national media coverage |
Technical and service impact:
| Score | Rating | Description |
|---|---|---|
| 1 | Low | Minor defect, no user effect |
| 2 | Low | Minor degradation with a workaround |
| 3 | Medium | Moderate service degradation, SLA at risk |
| 4 | Medium | Major outage or SLA breach |
| 5 | High | Critical system failure, data loss or serious security breach |
Add further dimensions (safety, legal, compliance) as your organisation requires.
Proximity is how soon the risk could occur. A moderate risk that is two weeks away may need more urgent attention than a serious risk that is a year away.
| Score | Label | Time until the risk could occur |
|---|---|---|
| 1 | Distant | More than 6 months |
| 2 | Remote | 3 to 6 months |
| 3 | Medium term | 1 to 3 months |
| 4 | Near | 2 to 4 weeks |
| 5 | Imminent | Less than 2 weeks |
Proximity does not change the overall score, but it affects action:
| Overall score | Rating | Colour |
|---|---|---|
| 1 to 4 | Low | Green |
| 5 to 9 | Medium | Amber |
| 10 to 16 | High | Red |
| 20 to 25 | Critical | Dark red |
| Probability (down) / Impact (across) | 1 | 2 | 3 | 4 | 5 |
|---|---|---|---|---|---|
| 5 | 5 Medium | 10 High | 15 High | 20 Critical | 25 Critical |
| 4 | 4 Low | 8 Medium | 12 High | 16 High | 20 Critical |
| 3 | 3 Low | 6 Medium | 9 Medium | 12 High | 15 High |
| 2 | 2 Low | 4 Low | 6 Medium | 8 Medium | 10 High |
| 1 | 1 Low | 2 Low | 3 Low | 4 Low | 5 Medium |
Risk: The payments provider's API specification is late. Our analysis shows that integration design cannot start until it arrives, and the provider has missed its last two deadlines.
Because the scoring uses defined bands, any other trained assessor with the same facts should arrive at the same figure.
Exercise 3.1: Score using the criteria. Score probability, impact (stating which dimension) and proximity for each risk on Project Meridian, then calculate the overall score and rating.
Exercise 3.2: Blind scoring. Each participant scores the same five risks without criteria (using Low, Medium, High). Record the results. Then repeat with the criteria tables above. Compare the spread of scores in each round. What does the difference tell you?
Exercise 3.3: Adapt the bands. Your organisation also runs £50,000 internal projects. Explain why a percentage-only financial scale may not suit both, and propose an adjustment (for example, adding absolute monetary thresholds).
| Risk | Probability | Impact | Proximity | Score | Rating |
|---|---|---|---|---|---|
| 1 | 4 (70%) | 3 (schedule: 5 weeks) | 3 (10 weeks) | 12 | High |
| 2 | 5 (confirmed) | 4 (financial: 6.5%) | 4 (3 weeks) | 20 | Critical |
| 3 | 2 (25%) | 2 (financial 1.9% and schedule 3 weeks both score 2) | 2 (6 months) | 4 | Low |
Use this worksheet for Exercise 3.1. Tap a cell to type.
| Risk | Probability | Impact (dimension) | Proximity | Score and rating |
|---|---|---|---|---|
| 1 | ||||
| 2 | ||||
| 3 |
Scoring tells you how serious a risk is. Tolerance tells you whether you can live with it. This module explains the difference between appetite and tolerance, shows how to set measurable thresholds by category and value, and demonstrates how tolerance drives the decision to act, accept or escalate.
Estimated study time: 90 minutes.
By the end of this module you will be able to:
| Risk appetite | Risk tolerance | |
|---|---|---|
| Meaning | The amount and type of risk the organisation is willing to pursue to achieve its goals | The maximum deviation from objectives the organisation will accept for a specific risk or project |
| Set by | Board or executive leadership | Executive leadership, applied by delivery and commercial leads |
| Nature | Strategic and broad | Specific, measurable thresholds |
| Example | We have a low appetite for security risk and a moderate appetite for schedule risk | We will not accept a security risk scored above 4 without executive approval |
Appetite is the philosophy. Tolerance turns it into numbers that people can apply.
Tolerance should be set:
Example tolerance table (illustrative):
| Category | Tolerable without special approval | Requires approval to carry |
|---|---|---|
| Financial | Residual score up to 9 | Residual score 10 and above |
| Schedule | Residual score up to 9 | Residual score 10 and above |
| Technical | Residual score up to 9 | Residual score 10 and above |
| Reputational | Residual score up to 6 | Residual score 8 and above |
| Security and compliance | Residual score up to 4 | Residual score 5 and above |
| Legal and contractual | Residual score up to 4 | Residual score 5 and above |
Notice that tolerance applies to the residual score. A risk may start as High, but if planned mitigation brings it within tolerance, the response is to deliver the mitigation, not to escalate for acceptance.
For each risk, ask:
Meridian has a risk scored 12 (High): the payments API specification is late. Schedule tolerance is 9. Mitigation is to build against a draft specification with an adapter layer, reducing the residual score to 6 (Medium). Residual 6 is within tolerance, so the risk can be managed by the project manager with the mitigation funded, provided it is delivered on time. If the adapter approach fails, the risk goes back above tolerance and escalates.
Exercise 4.1: Within tolerance? Using the table in 4.2, decide for each risk whether it can be carried without special approval.
Exercise 4.2: Set your thresholds. Draft a tolerance table for your own organisation. Decide whether you need different thresholds for contracts above and below £1m, and justify the split.
Exercise 4.3: Discussion. A senior leader asks to "just accept" a security risk that is above tolerance because the client is pressing for an early go-live. How should the framework handle this, and who needs to see the decision?
Good risk decisions compare what a risk could cost with what it costs to reduce it. This module shows how to estimate the cost of a risk materialising (including knock-on costs), estimate mitigation cost, calculate expected monetary value (EMV) and make a sound cost-benefit judgement.
Estimated study time: 90 minutes.
By the end of this module you will be able to:
Be thorough. Direct cost is usually the smaller part. Consider:
| Cost type | Examples in IT delivery |
|---|---|
| Direct cost | Rework, extra licences, additional testing, replacement resource |
| Time-related cost | Standing time for idle teams, extended hosting and environment costs, extended contractor fees |
| Contractual cost | Liquidated damages, service credits, withheld milestone payments |
| Revenue impact | Delayed billing, lost follow-on work |
| Reputational cost | Harder to quantify. Estimate through lost opportunity or remediation effort |
| Management time | Senior time diverted to recovery |
Record a range (best, most likely and worst case) where there is uncertainty, and state the basis of the estimate.
EMV = Probability (as a percentage) × Cost if it materialises
EMV gives a weighted figure that can be used to size contingency (Module 7) and to compare against mitigation cost.
Example: a 60% probability of a £130,000 cost has an EMV of £78,000.
EMV has limits. A 1% chance of a £10m loss has an EMV of only £100,000, but the organisation cannot afford the loss. Always read EMV alongside the score and tolerance.
Include:
Compare the reduction in exposure with the cost of mitigation.
Benefit of mitigation = EMV before mitigation − EMV after mitigation
A simple rule: mitigation is worth considering when its cost is clearly lower than the benefit, unless the risk is outside tolerance, in which case it may be necessary regardless of cost.
| Situation | Typical decision |
|---|---|
| Mitigation cost much lower than reduction in exposure | Mitigate |
| Mitigation cost similar to reduction in exposure | Consider other strategies, such as transfer or accept |
| Mitigation cost higher than the exposure | Accept or transfer, unless the risk is out of tolerance or safety, legal or security driven |
| Risk is out of tolerance and mitigation is too costly | Escalate for a decision |
Risk: key data migration engineer may leave (probability 40%).
Exercise 5.1: Cost the risk. For the risk "client may delay user acceptance testing by six weeks" on Meridian, list every cost category that applies and estimate best, most likely and worst-case figures. State your assumptions.
Exercise 5.2: Calculate and decide. For each case, calculate the EMV before and after mitigation and recommend whether to mitigate.
Exercise 5.3: Hidden costs. Identify at least three knock-on costs that are commonly missed when estimating the cost of a cloud outage during go-live week.
Once a risk is scored, costed and compared with tolerance, you need to decide what to do about it. This module covers the five response strategies, a simple way to choose between them, how to write a specific and measurable mitigation plan, and how to build a Path to Green plan that shows the route back to tolerance.
Estimated study time: 90 minutes.
By the end of this module you will be able to:
| Strategy | Meaning | IT example |
|---|---|---|
| Accept | Acknowledge the risk and take no action unless it occurs. May be passive (do nothing) or active (set aside contingency) | Minor licence variance covered by contingency |
| Avoid | Change the plan to remove the risk entirely | Drop a beta integration feature from scope |
| Reduce (mitigate) | Take action to lower probability, impact or both | Prototype a risky integration early |
| Transfer | Shift the consequence to a third party | Insurance, fixed-price supplier terms, back-to-back contract clauses |
| Share | Share the risk and reward with a partner | Joint-venture or risk-and-reward gain-share agreement |
Note that transfer moves the financial consequence, but usually not the accountability. If a subcontractor fails, the client still looks to you.
Use the following decision flow:
Often a combination works best, for example mitigate to reduce the probability and transfer part of the financial impact through contract terms.
A mitigation plan has to be specific and measurable. Minimum content:
| Element | Description |
|---|---|
| Objective | What the mitigation will achieve (for example, reduce probability from 4 to 2) |
| Actions | Specific, verifiable steps |
| Action owner | One named person per action |
| Due date | Date, not a vague "as soon as possible" |
| Cost | Effort and spend needed |
| Expected effect | Predicted residual probability, impact and score |
| Early warning indicator | What would tell us it is not working |
| Fallback (contingency plan) | What we will do if the risk occurs anyway |
| Secondary risks | New risks that the mitigation could create |
There is a difference between mitigation (acts before the risk occurs to reduce its likelihood or impact) and a contingency plan (acts after it occurs). Both should be recorded for important risks.
A Path to Green plan shows how a red or amber risk will return to an acceptable (green or within-tolerance) level. It is a milestone view of the mitigation plan, used for reporting to senior stakeholders.
A Path to Green includes:
Example for the payments API risk:
| Date | Milestone | Expected score | Status needed |
|---|---|---|---|
| Week 0 | Risk raised | 12 (red) | Not applicable |
| Week 2 | Draft specification obtained and adapter design approved | 9 (amber) | Provider commits to draft by week 2 |
| Week 5 | Adapter built and tested against draft | 6 (amber, within tolerance) | Test pass |
| Week 8 | Final specification received and confirmed compatible | 3 (green) | Provider sign-off |
Escalation trigger: if the draft specification is not obtained by week 3, the risk is reported to the programme director.
Exercise 6.1: Choose the strategy. For each Meridian risk, choose a primary strategy and justify it.
Exercise 6.2: Write a mitigation plan. For the risk "data migration may fail validation in UAT", write a mitigation plan using the table in 6.3, including at least four actions, owners, dates, expected residual score and an early warning indicator.
Exercise 6.3: Build a Path to Green. The risk "client decisions on interface design are three weeks late" currently scores 15 (red). Build a Path to Green with milestones that bring it to a score of 6 within eight weeks. Include one escalation trigger.
Answers to 6.2 and 6.3 will vary. Check that every action has a single named owner and a date, that the expected residual score is justified, and that the Path to Green has an escalation trigger.
Identifying and mitigating risk costs money, and some risks will materialise despite your best efforts. This module explains the difference between risk budget, contingency and management reserve, shows how to size contingency from the risk register using expected monetary value, and covers how contingency is controlled, drawn down, reported and released.
Estimated study time: 90 minutes.
By the end of this module you will be able to:
| Term | Meaning | Typical control |
|---|---|---|
| Risk budget | Money allocated to fund mitigation actions (the cost of reducing risks) | Project or programme manager |
| Contingency | Money (and time) held for identified risks that may materialise | Project or programme manager, with approval limits |
| Management reserve | Money held for unidentified risks ("unknown unknowns") | Senior management or sponsor |
Keep these distinct. Mixing them hides how much is being spent on prevention versus how much is held for consequences.
A common approach for identified risks is to sum EMVs.
| Risk | Probability | Cost if it occurs | EMV |
|---|---|---|---|
| Payments API late | 60% | £130,000 | £78,000 |
| Key engineer leaves | 15% | £105,000 | £15,750 |
| UAT delayed by client | 50% | £200,000 | £100,000 |
| Cloud price increase | 90% | £310,000 | £279,000 |
| Total EMV | £472,750 |
Points to remember:
Report regularly:
Release contingency when:
Released contingency usually returns to the organisation or boosts margin, according to policy. Releasing it too early creates a gap if new risks arise, so release should be approved formally.
Meridian has a contract value of £4.8m and a total EMV of £472,750 (9.9%). Leadership policy sets minimum contingency at 8% of contract value (£384,000) for projects with schedule or supplier risk. The EMV figure is higher, so the programme manager requests contingency of £472,750, with the portion above the 8% minimum (£88,750) needing approval from the programme director.
Exercise 7.1: Size the contingency. Using the risks in 7.2, remove the cloud price increase because a contract exception has been agreed, and recalculate. Compare the new total with a policy minimum of 8% of £4.8m. What do you recommend?
Exercise 7.2: Draw-down request. The payments API specification arrives six weeks late. Write a draw-down request covering the risk reference, the amount, the basis for the figure and the approval level needed, assuming the limits in 7.3.
Exercise 7.3: Release or hold? Phase 1 of Meridian is complete. £120,000 of contingency was held against Phase 1 risks and £35,000 has been drawn. Decide what to do with the remainder, and who must approve.
7.1. Removing £279,000 gives a total EMV of £193,750. The policy minimum is £384,000. Recommend holding the policy minimum, or seeking approval with evidence to hold less.
7.2. The expected cost is £130,000 (the figure used for this risk in 7.2). That is above the project manager's £50,000 limit and within the programme director's £250,000 limit, so the programme director approves. The request should cite the risk reference, show the basis (rework and standing time) and record the remaining contingency after draw-down.
7.3. £85,000 remains. Release it only when Phase 1 risks can no longer occur, with formal approval (programme director and finance). Any transfer to Phase 2 risks needs explicit approval.
Clear governance stops serious risks being managed by people without authority and stops minor risks absorbing senior time. This module introduces the Designated Authority Matrix (DAM), which says who owns a risk, and the escalation plan, which says who must be told or must decide. You will learn how the two differ and how to build both.
Estimated study time: 90 minutes.
By the end of this module you will be able to:
The DAM states which level of seniority must own and be responsible for managing a risk, based on its score. It exists so that serious risks are never managed by people without the authority to fund, decide or negotiate, and minor risks do not absorb senior time.
DAM compared with RACI:
| RACI | DAM | |
|---|---|---|
| Question answered | Who does what on a task or deliverable? | Who has the authority to own a risk of this size? |
| Based on | Activities and roles | Risk score, category and value |
| Structure | Roles mapped to tasks (Responsible, Accountable, Consulted, Informed) | Seniority levels mapped to score bands |
| Similarity | Both make accountability explicit and reduce ambiguity | Both make accountability explicit and reduce ambiguity |
A DAM can include RACI-style columns (who is Consulted or Informed at each level), which makes the two easy to combine.
Example DAM (illustrative):
| Current score | Rating | Risk owner (Accountable) | Day-to-day management (Responsible) | Consulted | Informed |
|---|---|---|---|---|---|
| 1 to 4 | Low | Workstream or team lead | Workstream lead | None required | Project manager |
| 5 to 9 | Medium | Project or delivery manager | Workstream lead | Specialist (technical, commercial) | Programme manager |
| 10 to 16 | High | Programme or delivery director | Project manager | Finance, legal, security as relevant | Executive sponsor |
| 20 to 25 | Critical | Executive (for example COO, CTO or managing director) | Programme director | Board members and relevant functional heads | Board or executive committee |
Category adjustments can be added on top:
| Category | Adjustment |
|---|---|
| Security and compliance | The security lead is always consulted; any risk above 4 is owned at least one level higher |
| Legal and contractual | Legal counsel is consulted for any risk above 4 |
| Financial | Finance director is consulted where exposure exceeds a set value |
| Reputational | Communications lead is consulted at 8 and above |
The escalation plan sets the criteria that trigger escalation: what must be raised, to whom, how fast, and what can be managed locally and autonomously.
Example escalation matrix (illustrative):
| Current score | Escalation requirement | Raise to | Timescale |
|---|---|---|---|
| 1 to 4 (Low) | Manage locally. No escalation | Not applicable | Reviewed monthly |
| 5 to 9 (Medium) | Manage within the project. Visible in the monthly report | Programme manager (informed) | Next report |
| 10 to 16 (High) | Escalate and agree response | Programme director | Within 2 working days |
| 20 to 25 (Critical) | Escalate immediately, with a proposed response and decision needed | Executive | Within 24 hours |
Escalation triggers that apply regardless of score:
What can be managed locally and autonomously? A risk can be managed locally when all of these are true: the score is within the local authority band, the residual score is within tolerance, no trigger above applies, and the cost of mitigation sits within delegated budget. The owner still records and reviews it.
Escalation must also work downward. When a risk reduces and stays in a lower band for an agreed period (for example, two review cycles), ownership can de-escalate.
| Ownership (DAM) | Escalation | |
|---|---|---|
| Question | Who manages this risk? | Who needs to be told or decide? |
| Driven by | Score and category | Score, trigger conditions, proximity, value |
| Example | A High risk is owned by the programme director | A Medium risk with an imminent proximity and a client executive involved is escalated even though it is owned by the project manager |
A risk can be escalated without changing owner (for information or a decision), and a risk can change owner without any escalation.
The Meridian cloud price increase scores 20 (Critical), with proximity 4. Under the DAM, the owner is an executive. Under the escalation plan, it must be raised within 24 hours with a proposed response (seek a contract exception, or revisit the price). The commercial lead is Consulted, and the executive sponsor and finance director are Informed.
Exercise 8.1: Assign the owner. Using the example DAM and category adjustments, state the owner level and who must be consulted.
Exercise 8.2: Escalate or not? For each risk, say whether to escalate, to whom and by when.
Exercise 8.3: Build your matrix. Draft a DAM and escalation matrix for a department of your choice. Define owner levels using real job titles, one category adjustment, and two escalation triggers that apply regardless of score.
8.1
8.2
Clients often ask suppliers to start work before a contract is signed, and teams and subcontractors commit costs quickly. This module explains what working at risk (W@R) means, how a W@R policy sets limits on commercial exposure, the conditions for an approved start, and how W@R links to the DAM, the escalation plan and the risk register.
Estimated study time: 90 minutes.
By the end of this module you will be able to:
Working at risk (W@R) means doing work, spending money or committing resources before there is a signed contract, a purchase order or other binding commitment to pay. If the contract is delayed, changed or never signed, the organisation may not be able to recover its costs.
W@R is common in IT because clients push for early starts and because internal teams, subcontractors and cloud services commit costs quickly. It is not forbidden, but it must be a deliberate, approved and limited decision, never an informal one.
A W@R policy defines what commercial risk can be carried without appropriate commercial cover and a commitment to pay. A strong policy covers:
| Element | What it sets out |
|---|---|
| Value limit | The maximum uncovered spend permitted at each approval level |
| Time limit | The maximum period work can continue without cover |
| Minimum commercial cover | The written evidence required before starting (for example, a letter of intent, an early works agreement or a signed client instruction with commitment to pay) |
| Approval levels | Who can approve each level |
| Conditions | Cost cap, scope limit, defined deliverables, stop-work date |
| Prohibited activity | What may never be done at risk |
| Tracking and reporting | A W@R register and regular reporting of exposure |
Example W@R policy (illustrative):
| Level | Maximum uncovered exposure | Maximum duration | Minimum commercial cover | Approver |
|---|---|---|---|---|
| 1 | Up to £25,000 | 4 weeks | Written client instruction from an authorised signatory | Delivery manager and commercial manager |
| 2 | £25,001 to £100,000 | 8 weeks | Letter of intent or early works agreement with a commitment to pay up to a cap | Delivery director and finance director |
| 3 | Above £100,000 or over 8 weeks | Case by case | Signed early works agreement with capped value and payment terms | Executive (commercial director or CFO) |
Prohibited at risk, in this example policy:
On Meridian, the client wants build to start next month. Contract variations worth £620,000 are still being negotiated. The first six weeks of work will cost about £180,000, including £45,000 of subcontractor commitment.
Using the example policy:
Exercise 9.1: Which level? State the level, approver and minimum cover for each request under the example policy.
Exercise 9.2: Spot the breach. Identify which W@R conditions are not met in this request: "The client told us verbally to proceed. We have engaged the subcontractor for 10 weeks. We expect the contract to be signed soon."
Exercise 9.3: Write the case. Prepare a W@R approval request for the Meridian situation. Include exposure, cover, conditions, stop-work date, risk score and approver.
9.1
9.2 There is no written instruction, no commitment to pay, no cap or stop-work date, no approval, no back-to-back cover with the subcontractor and no register entry.
A well-managed risk is only useful if the right people know about it at the right time. This module covers how to build a communication plan, which reports suit which audiences, how to communicate with clients, suppliers and senior leaders, and how to run effective risk reviews.
Estimated study time: 90 minutes.
By the end of this module you will be able to:
A communication plan sets out who needs to know what, when, in what format, and who is responsible for telling them.
| Audience | What they need | Format | Frequency | Owner |
|---|---|---|---|---|
| Project team | Risks they own, new risks, upcoming mitigation actions | Risk review, team meeting | Weekly | Project manager |
| Programme or delivery director | Top risks, High and Critical risks, Path to Green status, contingency position | Risk summary, dashboard | Fortnightly, plus on escalation | Programme manager |
| Executive and board | Critical risks, decisions needed, W@R exposure, trend | One-page summary | Monthly or quarterly, plus immediate escalation | Programme director |
| Client | Shared risks, client dependencies, joint mitigation | Joint risk register, client review meeting | As contractually agreed | Delivery lead |
| Suppliers | Risks they own or influence, deadlines | Supplier review meeting | Monthly | Supplier manager |
| Finance and commercial | Exposure, contingency, W@R | Financial report | Monthly | Commercial manager |
Principles:
| Report | Purpose |
|---|---|
| Risk register extract | Detailed record for the project team |
| Heat map | Shows how many risks sit in each cell of the matrix, before and after mitigation |
| Top risks report | The top five to ten risks with owner, score, trend, mitigation status and decision needed |
| Path to Green tracker | Progress of red and amber risks to tolerance |
| Trend report | Number of risks by rating over time, new, closed and escalated risks |
| Contingency report | Original, drawn and remaining contingency against remaining EMV |
| W@R register | Exposure, cover status, stop-work dates and approvals |
For each top risk, show the trend (rising, stable or falling) and whether a decision is needed.
Clients. Share risks that the client can influence, such as late decisions or data availability. Be careful with commercially sensitive risks (internal cost, margin, W@R). Agree what is shared and how.
Suppliers. Share the specific risks they own, with dates and consequences. Record agreed actions and follow up in writing.
Senior leaders. Lead with the decision needed and the exposure, then the options and your recommendation. Keep to one page.
| Review | Frequency | Participants | Focus |
|---|---|---|---|
| Project risk review | Weekly (30 minutes) | Project manager and risk owners | New risks, proximity 4 and 5 risks, overdue actions |
| Programme risk review | Monthly | Programme director, project managers, commercial and finance | High and Critical risks, Path to Green, contingency, escalations |
| Executive risk review | Monthly or quarterly | Executives | Critical risks, W@R, decisions, tolerance |
| Framework review | Annually | Risk manager, PMO, leadership | Criteria, DAM, tolerance, W@R policy and lessons learned |
Sample weekly agenda:
Exercise 10.1: Build the plan. Create a communication plan for Meridian covering at least six audiences. State content, format and frequency.
Exercise 10.2: One-page summary. Using the risks from Modules 3, 5 and 9, write a one-page executive summary showing the top three risks, their scores, trend, exposure and the decisions you need.
Exercise 10.3: Critique a report. A monthly report lists 48 risks in score order with no owners, trends or decisions. List five improvements.
Possible improvements: show only the top five to ten risks, add an owner to each, show the trend arrow, state the decision needed, group risks by category or workstream, show Path to Green status for red risks, add contingency and W@R positions, and keep the full register as an appendix.
This final module brings every part of the framework into one end-to-end case study. You will also review the common pitfalls that undermine risk management in practice, learn how to improve the framework over time, and complete the course assessment.
Estimated study time: 90 minutes, plus time for the practical assessment.
By the end of this module you will be able to:
Scenario. Project Meridian is four months in. The following has happened:
Task. Work through the framework in order and produce the outputs shown.
| Step | Action | Output |
|---|---|---|
| 1 | Identify and write risk statements (cause, event, effect) | At least four risks |
| 2 | Categorise (primary and secondary) | Categories for each |
| 3 | Score using the criteria (probability, impact, proximity) | Scores and evidence |
| 4 | Compare to tolerance | Within or outside tolerance |
| 5 | Estimate the cost of the risk and the mitigation | EMV and cost-benefit |
| 6 | Choose a response strategy and write a mitigation plan | Strategy and plan |
| 7 | Create a Path to Green for any red risk | Milestones and triggers |
| 8 | Assign owner (DAM) and decide escalation | Owner and escalation route |
| 9 | Assess the W@R position and approval level | W@R request |
| 10 | Check contingency and risk budget | Draw-down or sufficiency view |
| 11 | Plan communication | Who is told what, and when |
Facilitator notes. Run the exercise in groups of four. Ask each group to present its top risk and its escalation decision. Compare groups' scores against the criteria and discuss any differences.
| Pitfall | Why it matters | Remedy |
|---|---|---|
| Inconsistent scoring | Reports cannot be compared | Defined criteria, calibration sessions |
| Stale register | Decisions are based on old information | Review cadence, last review date on each risk |
| Mitigation without owners or dates | Actions never happen | Mandatory owner and date fields |
| Optimistic residual scores | False confidence | Evidence for residual score, independent challenge |
| Escalating everything, or nothing | Leaders overwhelmed or blind | DAM and escalation criteria |
| Informal W@R | Unrecoverable cost | W@R policy and register |
| Ignoring proximity | Imminent risks treated as distant | Proximity rules in review |
| Treating transfer as removal | Accountability remains | Monitor transferred risks |
| Contingency as a slush fund | No control or learning | Named risks and draw-down approval |
End-of-course assessment: 25-question knowledge check
The final quiz covers Modules 1 to 11. Pass mark: 20 out of 25 (80%). Passing unlocks the course badge and certificate.
Part B: Practical assessment. Using a real or provided project scenario, produce:
Marking criteria:
| Criterion | Weight |
|---|---|
| Risk statements are clear and categorised correctly | 15% |
| Scoring is consistent with criteria and evidenced | 20% |
| Response strategy and mitigation plan are specific and costed | 20% |
| Ownership and escalation follow the DAM and plan | 15% |
| Contingency and W@R are handled correctly | 15% |
| Communication is clear and decision-focused | 15% |
Practical assessment guidance: use the marking criteria below to review the quality and completeness of your work. The final quiz pass mark is 20 out of 25 (80%).